LDI Property: History
Significant palladium mineralization was first discovered in the Roby Zone in 1963 by prospectors. Various exploration programs were undertaken over the next 25 years by a number of companies, including Gunnex, Anaconda, Texas Gulf Sulphur, and Boston Bay Mines.
In 1990, Madeleine Mines Ltd. developed the property. After intermittent production and continuing capital expenditures, commercial open pit production of the Roby Zone was achieved in December 1993. The Company was formed as an outcome of corporate reorganization. In 2000, LDI commenced an expansion program at the Lac des Iles mine and a new mill was commissioned in the second quarter of 2001, which achieved its nominal rated 15,000 tonnes per day throughput in August 2002.
A major Phase 4 push back of the south and east pit wall was undertaken in 2004-2005, with waste removal of upper benches completed in 2005. In 2006, the open pit mine was redesigned to address south wall slope stability issues. This pit redesign was finalized in September 2006.
From 1999 to 2001, the Company’s exploration arm carried out an extensive drilling campaign on behalf of LDI that identified mineralization at depth, below the ultimate pit bottom. The drilling identified two zones with potential for underground mining: the Main High Grade Zone and the Offset Zone.
On July 31, 2003, Roscoe Postle Associates Inc. (“RPA”) completed a positive pre-feasibility study for underground mining of the Main High Grade Zone (down dip extension of the open pit Main Zone) at the Lac des Iles mine on behalf of LDI. Subsequently, RPA completed a feasibility study for the underground mine dated February 27, 2004. The study proposed to develop a 2,000 tonnes per day underground mine to run concurrently with the existing open pit mine. A NI 43-101 Technical Report by RPA dated April 2, 2004, summarized LDI’s underground project at the mine as of March 31, 2004.
Underground development on the High Grade Zone below the Roby pit started in 2004, with the ramp developed and the zone accessed in late 2005. Development muck was delivered to the concentrator in December 2005 and underground commercial production began in April 2006.
The Offset Zone was discovered in 2001 by the Company. The Offset Zone is the fault offset, down dip extension of the High Grade Zone that is currently being mined underground below the Roby open pit at the Lac des Iles mine. From 2001 to 2006 some 63 holes totalling 62,022 metres from both underground and surface diamond drilling programs have explored the Offset Zones. The 2006 drilling was planned to confirm grade continuity at hole spacing in the zone of 50 metres by 50 metres and upgrade a portion of the inferred resources to indicated resources. From May to October 2007, the Company completed approximately 18,000 metres of infill drilling in the upper 300 metres of the Offset Zone, with the objective of upgrading that portion of the mineral resources to the measured and indicated categories.
On February 23, 2007 Scott Wilson RPA completed an independent estimate of mineral resources of the Offset Zones, which was updated in January 2009 to reflect the results of additional drilling. The Offset Zone has been traced from 311,600N to 312,125N on strike (525 metres) and vertically from –60 RL to –550 RL (490 metres) at depths of 575 metres to 1,065 metres. The current 2009 drilling program is being completed from a 5095RL exploration drift targeting the upper portion of the Offset Zone. |